Spring is coming to Småland and a sure sign of spring is the track work week that occurs every year in connection with the Easter holidays. We plan to work with signals, track and vehicles.
We welcome both active members and interested parties to visit us and learn about our activities. You are welcome to contact Peter Sjöquist(psj*snabela*psj.nu) or Dennis Blomfeldt(dennisbolmfeldt*snabela*hotmail.com) if you are interested in getting an introduction.
The work schedule for the week: (changes may be made if necessary)
Saturday | 4/4 | Dismantling and loading of signalling material, Nybro |
Sunday | 5/4 | Ditto and Labour Day Hultsfred-Målilla(Hultsfred branch of the association) |
Monday | 6/4 | Grinding, cutting and preliminary transport (Hultanäs-Virserum) with locomotive + wagon during the evening. |
Tuesday | 7/4 | Spring overhaul of the slipway changer in the morning, then slipway replacement at Lake Virserum |
Wednesday | 8/4 | Continued replacement of slipways Hjortöström-Virserum |
Thursday | 9/4 | -”- |
Friday | 10/4 | -”- |
Saturday | 11/4 | Track work in Triabo |
Sunday | 12/4 | Continued track work in Triabo and some sleeper replacement at the same location |
Monday | 13/4 | Cleaning day at Gårdveda railway yard, various track work |